Files around 20182368MNBT950588024F0000000426225I003.pdf

(View all drawers)
Title Documents
[TABLE OF CONTENTS]
[ORDERS] OPERATIONS ORDERS NUMBER 17 [WITH ATTACHMENT]
[REPORT REGARDING DETAILED RECONNAISSANCE REPORT]
[REPORT REGARDING NARRATIVE]
[TABLE] MAN HOURS CONSUMED
[TABLE] MATERIALS CONSUMED
[TABLE] EQUIPMENT HOURS
[DIAGRAM] NORTH PROJECT [WITH ATTACHMENTS]
[PHOTOGRAPH WIDE SHOT OF A SET OF ROADWAYS SURROUNDED BY MOUNTAINS [WITH ATTACHMENTS]
[DIAGRAM] REVISIONS
[COVER] EIGHTH ARMY TRAINING AIDS CENTER
[CORRESPONDENCE FROM CLAUD E. PERKINS TO 24TH ENGINEER CONSTRUCTION GROUP REGARDING PROJECT HISTORY, EIGHTH ARMY TRAINING AIDS CENTER]
[TITLE PAGE] EIGHTH ARMY TRAINING AIDS CENTER
[TABLE OF CONTENTS]
[ORDERS] OPERATIONS ORDERS NUMBER 71
[REPORT REGARDING EIGHTH ARMY TRAINING AIDS CENTER NARRATIVE]
[TABLE] MAN HOURS EXPENDED ON THE PROJECT
[TABLE] EQUIPMENT HOURS EXPENDED ON THE PROJECT
[TABLE] BILL OF MATERIALS [WITH ATTACHMENTS]
[DIAGRAM] PROPOSED TYPE D TRAINING AIDS SUBCENTER
[PHOTOGRAPH WIDE SHOT OF AN EMPTY, RECTANGULAR CONSTRUCTION SITE NEAR A ROAD WITH ATTACHMENTS]
[COVER] HEMORRHAGIC FEVER CENTER
[TITLE PAGE] HEMORRHAGIC FEVER CENTER
[TABLE OF CONTENTS]
[ORDERS] 400 BED HEMORRHAGIC FEVER CENTER [WITH ATTACHMENTS]
[REPORT REGARDING HEMORRHAGIC FEVER CENTER NARRATIVE]
[LIST OF JOB PERSONNEL]
[OUTLINE] SPECIFICATIONS
[TABLE] MAN HOURS EXPENDED ON THE PROJECT
[TABLE] EQUIPMENT HOURS EXPENDED ON THE PROJECT
[TABLE] MATERIALS LIST FOR HEMORRHAGIC FEVER CENTER
[PHOTOGRAPH HIGH ANGLE WIDE SHOT OF THE HEMORRHAGIC FEVER CENTER WITH ATTACHMENTS]
[DIAGRAM] HEMORRHAGIC FEVER CENTER ELECTRICAL DISTRIBUTION [WITH ATTACHMENTS]
[REPORT] HISTORICAL DOCUMENT, HIGHWAY BRIDGE CS5871 ROUTE 18 SEOUL CHUNCHON [WITH ATTACHMENT]
[DIAGRAM] AS BUILT PLANS -HW'Y BRIDGE AT KUAM-NI [WITH ATTACHMENTS]
[REPORT] HISTORICAL DOCUMENT, HIGHWAY BRIDGE CS8894 ROUTE 18 SEOUL CHUNCHON
[DIAGRAM] AS BUILT PLANS OF CHUNCHON HWY. BRIDGE CS - 8994 [WITH ATTACHMENTS]
[COVER] PROJECT HISTORY, REHABILITATION OF TIDAL LOCKS, INCHON, KOREA
[DIAGRAM] DIAGRAM OF DEMOLITION CHARGES USED TO DESTROY TIDAL BASIN LOCKED GATES (4 JANUARY 1951) [WITH ATTACHMENT]
[PHOTOGRAPH WIDE SHOT OF SEVERAL MEN WORKING ON A DOCK AND ON THE SHIP TO THE LEFT
[DIAGRAM] LOCK GATE CHAMBER [WITH ATTACHMENT]
[PHOTOCOPY OF JINSEN DOCK DIAGRAM]
[PHOTOCOPY OF PROJECT PROGRESS CHART]
[PHOTOCOPY OF TURNBUCKLES FOR LOCK GATES]
[PHOTOCOPY OF TURNBUCKLE ON GATE NO. 1]
[PHOTOCOPY OF REBUILDING GATE NO. 2]
[PHOTOCOPY OF REBUILDING GATE NO. 3
[PHOTOCOPY OF GATE NO. 4, REBUILT]
[COVER]
[TITLE PAGE] REPORT OF COMPLETION, ROAD AND TRAMWAY CONSTRUCTION
[TABLE OF CONTENTS] REPORT OF COMPLETION, ROAD AND TRAMWAY CONSTRUCTION
[REPORT] REPORT OF COMPLETION, ROAD AND TRAMWAY CONSTRUCTION
[PHOTOGRAPH WIDE SHOT TRAMWAY NO. 1 - TRACK CABLE RAISED - VIEW FROM TOP OF RIDGE TOWARD LOWER TERMINAL WITH ATTACHMENTS]
[DIAGRAM] GROOMS TRAMWAY [WITH ATTACHMENTS]
[REPORT] CONSTRUCTION PROJECT HISTORY, BORDER PATROL ROAD
[REPORT] PROJECT HISTORY, CONSTRUCTION OF A SEMI-PERMANENT STREAM CROSSING
[REPORT] PROJECT HISTORY, CONSTRUCTION OF A 6TH R.O.K. DIVISION SUPPLY ROUTE
[REPORT] PROJECT HISTORY, CONSTRUCTION OF A SEMI-PERMANENT STREAM CROSSING
[REPORT] PROJECT HISTORY, CONSTRUCTION OF A 6TH R.O.K. DIVISION SUPPLY ROUTE
[REPORT] PROJECT HISTORY OF HANGYE BY-PASS
[REPORT] PROJECT HISTORY OF HANGYE BY-PASS
COMPLETION REPORT ON ACCESS ROAD TO HILL 915
COMPLETION REPORT ON ACCESS ROAD TO HILL 915
[REPORT] CONSTRUCTION PROJECT HISTORY OF TWINNAN RIVER, HOENGSONG, KOREA
[REPORT] CONSTRUCTION PROJECT HISTORY OF TWINNAN RIVER, HOENGSONG, KOREA
COMPLETION REPORT ON YANGGU BRIDGE DT123153
COMPLETION REPORT, TRAMWAY 1220
COMPLETION REPORT, TRAMWAY 1220
PROJECT COMPLETION REPORT [FOR] CONTROL TOWER DT112150
ENGINEER DOCUMENT COLLECTION; BOX 25A, FOLDER 11, COMPLETION REPORT ON SANGU-MANG BRIDGE D127202, 19 MAY 1952
PROJECT COMPLETION REPORT CONTROL TOWER D112150
[REPORT] CONSTRUCTION PROJECT HISTORY COMBAT ROAD CONSTRUCTION
[REPORT] CONSTRUCTION PROJECT HISTORY COMBAT ROAD CONSTRUCTION
[REPORT] CONSTRUCTION PROJECT HISTORY COMBAT ROAD CONSTRUCTION
[REPORT] CONSTRUCTION PROJECT HISTORY COMBAT ROAD CONSTRUCTION
[REPORT] ANCHORING OF FLOATING MILITARY EQUIPMENT IN A STREAM OF HIGH VELOCITY
[REPORT] ENGINEER STATUS ROKA
[REPORT] ENGINEER STATUS ROKA
FLOOD REPORT
FLOOD REPORT
FLOOD REPORT
STATUS REPORTS
STATUS REPORTS
FLOOD REPORT
GENERAL ORDERS NUMBER 486
[REPORT] CRITERIA FOR CONSTRUCTION OF KOREAN THEATER OF OPERATION AIR BASES
REPORT OF CONSTRUCTION OF AIRFIELD LANDING STRIPS AT K-2, K-16, AND K-1, OF FIFTH AIR FORCE KOREA
ENGINEER PERIODIC OPERATIONS REPORT NUMBER 1
ENGINEER PERIODIC OPERATIONS REPORT NUMBER 3
ENGINEER PERIODIC OPERATIONS REPORT NUMBER 10
ENGINEER PERIODIC OPERATIONS REPORT NUMBER 2
ENGINEER PERIODIC OPERATIONS REPORT NUMBER 11
ENGINEER PERIODIC OPERATIONS REPORT NUMBER 12
ENGINEER PERIODIC OPERATIONS REPORT NUMBER 19
ENGINEER PERIODIC OPERATIONS REPORT NUMBER 17
ENGINEER PERIODIC OPERATIONS REPORT NUMBER 14
ENGINEER PERIODIC OPERATIONS REPORT NUMBER 24
ENGINEER PERIODIC OPERATIONS REPORT NUMBER 23
ENGINEER PERIODIC OPERATIONS REPORT NUMBER 22
ENGINEER PERIODIC OPERATIONS REPORT NUMBER 21
ENGINEER PERIODIC OPERATIONS REPORT NUMBER 20